The following chart includes each of the conditions that intervening parties have proposed in the record for Maryland Public Service Commission Case No. 8997, In the Matter of the Application of Catoctin Power, LLC for a Certificate of Public Convenience and Necessity to Construct a Generating Station in Frederick County Maryland. The chart also includes two conditions that Catoctin Power, LLC (Catoctin Power) is proposing pursuant to Mr. Gordon Chirdon’s rebuttal testimony. Except as otherwise noted, Catoctin Power supports each of the conditions set forth below. Moreover, Catocitin Power has been working with the Maryland state agencies to develop Proposed Final Conditions that address Catoctin Power’s few concerns regarding the state agencies’ Draft Conditions Currently In The Record. Catoctin Power has developed the Proposed Final Conditions based on these discussions and the Status Column identifies as “agreed” each of the Proposed Final Conditions for which we believe that Catoctin Power and the state agencies have reached agreement. The Status Column identifies as “pending” each of the Proposed Final Conditions for which Catoctin Power and the state agencies have not yet reached agreement. Catoctin Power and the state agencies are continuing to discuss these few outstanding conditions. Frederick County has not been available to discuss Frederick County’s Draft Conditions Currently In The Record with Catoctin Power. Therefore, the status of each Frederick County condition is marked as “pending.” Catoctin Power disagrees with Mr. Don James’ Draft Conditions Currently In The Record for the reasons set forth in Catoctin Power’s rebuttal testimony and this chart. Therefore, the status of each Don James condition is marked as “pending.”
|
INDEX NO. |
DRAFT CONDITION CURRENTLY IN THE RECORD |
PROPOSED FINAL CONDITION |
COMMENTS |
STATUS |
|
Catoctin Power |
||||
|
Catoctin-1 |
To be added to a section entitled “General Requirements”:
Except as otherwise provided for in the following provisions, the application for the Certificate of Public Convenience and Necessity (CPCN) is considered to be part of this CPCN for the Catoctin Power Project. The application consists of the original application received by the Maryland Public Service Commission (PSC) on February 25, 2004 and subsequent amendments provided in testimony filed by Catoctin Power, LLC on June 3, 2004, August 20, 2004, August 26, 2004 and December 23, 2004. Construction of the facility shall be undertaken in accordance with the CPCN application and subsequent amendments. If there are any inconsistencies between the conditions specified below and the application, the conditions in this CPCN shall take precedence; and if there are any inconsistencies between the conditions in this CPCN and applicable federal and state statutes or regulations, the applicable federal and state statutes or regulations shall take precedence. |
No change. |
Catoctin Power has proposed the Draft Condition Currently In The Record. PPRP has a proposed a similar condition in its conditions set forth under the heading “Air Quality.” Catoctin Power believes this condition has general application, and should be added as a general condition applicable to all CPCN conditions. Moreover, for purposes of this Draft Condition Currently In The Record, Catoctin Power believes it is important to define the term “subsequent amendments” so there is no confusion regarding the “application” with which Catoctin Power is required to comply. Finally, the PPRP’s proposed conditions incorporate several State and federal laws, which are paraphrased for purposes of the proposed CPCN conditions. Because paraphrased language is necessarily incomplete, Catoctin Power believes it is important to clarify, in the General Conditions, that if there are any inconsistencies between the conditions specified in the CPCN and applicable federal or state statues or regulations, the applicable federal or state statutes or regulations shall take precedence.
Catoctin Power fully supports the Draft Condition Currently In The Record, and respectfully requests that that the PSC include the Draft Condition Currently In The Record in any CPCN. |
Agreed |
|
Catoctin-2 |
To be added to a section entitled “General Requirements”:
If any provision of this CPCN shall be held invalid for any reason, the remaining provisions shall remain in full force and effect and such invalid provision shall be considered severed and deleted from this CPCN.
|
No change. |
Catoctin Power has proposed the Draft Condition Currently In The Record. PPRP has proposed a similar condition in its conditions set forth under the heading “Air Quality.” Catoctin Power believes this condition has general application, and should be added as a general condition applicable to all CPCN conditions.
Catoctin Power fully supports the Draft Condition Currently In The Record, and respectfully requests that that the PSC include the Draft Condition Currently In The Record in any CPCN. |
Agreed |
|
PPRP and Other State Agencies’ |
||||
|
PPRP-1 |
Except as otherwise provided for in the following provisions, the application for the Certificate of Public Convenience and Necessity (CPCN) is considered to be part of this CPCN for the Catoctin Power Project. The application consists of the original application received by the Maryland Public Service Commission (PSC) on February 25, 2004 and subsequent amendments. Construction of the facility shall be undertaken in accordance with the CPCN application and subsequent amendments. If there are any inconsistencies between the conditions specified below and the application, the conditions in this CPCN shall take precedence. In the application, estimates of dimensions, volumes, emission rates, operating rates, feed rates and hours of operation are not deemed to constitute enforceable numeric limits except to the extent that they are necessary to make a determination of compliance with applicable regulations. |
|
Agreed |
|
|
PPRP-2 |
The application for a CPCN includes the application for Prevention of Significant Deterioration (PSD) approval, Nonattainment Area New Source Review (NA-NSR) approval, and air quality construction permits. The CPCN serves as the PSD approval, NA-NSR approval, and air quality construction permit and does not constitute the permit to construct or approvals until such time as Catoctin Power has provided documentation demonstrating that nitrogen oxides (NOx) emission offsets totaling at least 249 tons and volatile organic compound (VOC) emission offsets totaling at least 39 tons have been obtained and approved by the Maryland Department of the Environment and are federally enforceable. |
No change. |
|
Agreed |
|
PPRP-3 |
For air permitting purposes, the Catoctin Power Project shall include: 1) two, GE Model 7FA, natural gas-fired combustion turbines with dry low-NOx combustors, duct burners rated at 577 million Btu per hour (MMBtu/hr, higher heating value) heat recovery steam generating units (HRSGs) equipped with selective catalytic reduction (SCR) and oxidation catalyst systems, and a steam turbine, combined plant rated at nominal 600 megawatt; 2) one nominal 1,000-kilowatt, EPA Tier 1-rated diesel-fired emergency diesel generator; 3) one nominal 350-kilowatt, EPA Tier 1-rated diesel-fired emergency diesel generator at the water supply pump house; 4) one 370-horsepower, diesel-fired firewater pump engine; and 4) one multi-cell cooling tower equipped with drift eliminators. |
No change. |
|
Agreed |
|
PPRP-4 |
Definitions:
ii) Entered into binding agreements or
contractual obligations which cannot be canceled or modified without
substantial loss to the owner or operator, to undertake a continuous
program of actual construction or modification of the source to be
completed within a reasonable time.
b) "Startup" shall be
defined as the period of time from initiation of combustion firing until
the unit reaches at least 60% load. Periods of cold startup shall last
no more than 4 hours; periods of warm/hot startup shall last no more
than 2 hours.
c) "Shutdown" is defined as that period of time that the turbine
output is lowered with the intent to shut down, until the point at which
the load drops below 60%. Periods of shutdown shall last no more than
30 minutes. d) “Administrator” is defined as the Secretary of the Maryland Department of the Environment. |
No change. |
|
Agreed |
|
PPRP-5 |
Catoctin Power shall construct exhaust stacks for the heat recovery steam generators downstream of the construction turbines with a vertical height of at least 160 feet above ground level. |
No change. |
|
Agreed |
|
PPRP-6 |
If any provision of this CPCN shall be held invalid for any reason, the remaining provisions shall remain in full force and effect and such invalid provision shall be considered severed and deleted from this CPCN. |
No change. |
|
Agreed |
|
PPRP-7 |
Representatives of the Maryland Department of the Environment (MDE) and the Frederick County Health Department shall be afforded access to the Catoctin Power facility at any reasonable time to conduct inspections and evaluations necessary to assure compliance with the CPCN requirements. Catoctin Power shall provide such assistance as reasonably may be necessary to conduct such inspections and evaluations by such representatives of MDE effectively and safely, which may include but need not be limited to the following:
|
No change. |
|
Agreed |
|
PPRP-8 |
This CPCN constitutes the PSD approval, the NA-NSR approval, and air quality construction permit for the Catoctin Power Project. In accordance with COMAR 26.11.02.04B, the air quality provisions expire if, as determined by MDE, Air and Radiation Management Administration (ARMA): Construction is not commenced within 18 months after the date of issuance of a final CPCN; Construction is substantially discontinued for a period of 18 months or more after it has commenced; or Construction is not completed within a reasonable period of time after the issuance of a final CPCN. |
No change. |
|
Agreed |
|
PPRP-9 |
At least 60 days prior to the anticipated date of start-up of the combustion turbines, Catoctin Power shall submit to ARMA:
a) An application for a temporary permit to operate; and b) The required documentation confirming the acquisition of nitrogen oxides (NOx) allowances from sources approved by ARMA for the first ozone season in which the facility will operate. |
No change. |
|
Agreed |
|
PPRP-10 |
All requirements pertaining to air quality that apply to Catoctin Power shall apply to all subsequent owners and/or operators of the facility. In the event of any change in control or ownership, Catoctin Power shall notify the succeeding owner/operator of the existence of the requirements of this CPCN pertaining to air quality by letter and shall send a copy of that letter to MDE ARMA. |
No change. |
|
Agreed |
|
PPRP-11 |
The Catoctin Power facility is subject to all applicable federally enforceable State air quality requirements including, but not limited to, the following regulations:
a) COMAR 26.11.01.04A-C Requires Catoctin Power to follow test methods in §C of this regulation to determine compliance. ARMA may require Catoctin Power to install, use, and maintain monitoring equipment or employ other methods as specified by ARMA to determine the quantity or quality, or both, of emissions discharged into the atmosphere and to maintain records and make reports on these emissions to ARMA in a manner and on a schedule approved by ARMA or the control officer. b) COMAR 26.11.01.05-1 Emissions Statements—Requires Catoctin Power to submit a certified, facility-wide emissions statement to ARMA by April 1st of each year. c) COMAR 26.11.01.07C Malfunctions and Other Temporary Increases of Emissions—Requires Catoctin Power to report the onset and the termination of the occurrence of excess emissions, expected to last or actually lasting for 1 hour or more, to ARMA by telephone. d) COMAR 26.11.02.19A Fee Schedule—Requires Catoctin Power to pay annual Title V operating permit fees. e) COMAR 26.11.03.01 Applicability and General Requirements—Requires Catoctin Power to apply for and obtain a Title V (Part 70) operating permit. f) COMAR 26.11.06.02C(1) Visible Emissions—Prohibits Catoctin Power from causing or permitting the discharge of emissions from any installation or building, other than water in an uncombined form, which is greater than 20% opacity. The visible emissions standards in §C of COMAR 26.11.06.02C do not apply to emissions during startup and process modifications or adjustments, or occasional cleaning of control equipment, if: (a) the visible emissions are not greater than 40% opacity; and (b) the visible emissions do not occur for more than 6 consecutive minutes in any 60-minute period. g) COMAR 26.11.06.03C(1) Particulate Matter From Unconfined Sources—Prohibits Catoctin Power from causing or permitting emissions from an unconfined source without taking reasonable precautions to prevent particulate matter from becoming airborne. h) COMAR 26.11.06.03D Particulate Matter From Materials Handling and Construction—Prohibits Catoctin Power from causing or permitting any material to be handled, transported, or stored, or a building, its appurtenances, or a road to be used, constructed, altered, repaired, or demolished without taking reasonable precautions to prevent particulate matter from becoming airborne. i) COMAR 26.11.06.14 Control of PSD Sources—Which prohibits Catoctin Power from constructing, modifying, or operating, or causing to be constructed, modified, or operated, a Prevention of Significant Deterioration (PSD) source, as defined in COMAR 26.11.01.01B(37), which will result in violation of any provision of 40 CFR §52.21, 2002 edition, except that the reviewing authority is the Department instead of the U.S. EPA Administrator unless otherwise specified in 40 CFR §52.1116, and the applicable procedures are those set forth in COMAR 26.11.02. j) COMAR 26.11.17.03B(3) Requirements for Major New Sources and Modifications, General Conditions—Requires Catoctin Power to meet the reasonable further progress requirements in §173(a)(1)(A) of the Clean Air Act by obtaining emission reductions (offsets) of the same pollutant from existing sources in the area of the proposed source, whether or not under the same ownership, at a minimum ratio of 1.3 to 1 for sources of NOx and VOCs in Frederick County, Maryland.
|
No change.
|
|
Agreed |
|
PPRP-12 P |
The Catoctin Power facility is subject to all applicable State-only enforceable air quality requirements including, but not limited to, the following regulations:
b) COMAR 26.11.02.19C Information Required to be Maintained by Source—Requires Catoctin Power to maintain records necessary to support the emission certification. c) COMAR 26.11.02.19D Emission Certification—Requires Catoctin Power to certify, as provided at Regulation .02F of this chapter, the actual emissions of regulated air pollutants from all installations at the plant or facility. Certification shall be on a form obtained from ARMA and shall be submitted to ARMA not later than April 1 of the year following the year for which certification is required. An emission certification submitted pursuant to this section and which contains all information required by COMAR 26.11.01.05-1, for NOx and VOC, satisfies the requirements of COMAR 26.11.01.05-1. d) COMAR 26.11.06.08 Nuisance—Prohibits Catoctin Power from operating or maintaining a source in such a manner that a nuisance is created. e) COMAR 26.11.06.09 Odors—Prohibits Catoctin Power from causing or permitting the discharge into the atmosphere of gases, vapors, or odors beyond the property line in such a manner that a nuisance or air pollution is created. |
No change. |
|
Agreed |
|
PPRP-13 P |
The combustion turbines and associated duct burners and heat recovery steam generators at the Catoctin Power facility are each subject to all applicable federally enforceable State air quality requirements including, but not limited to, the following regulations: a) COMAR 26.11.06.12 Control of NSPS Sources—Prohibits Catoctin Power from constructing, modifying, or operating, or causing to be constructed, modified, or operated, a New Source Performance Standard (NSPS) source as defined in COMAR 26.11.01.01C, which results or will result in violation of the provisions of 40 CFR 60, 2002 edition. b) COMAR 26.11.09.05A(1) Visible Emissions—Except as provided in COMAR 26.11.09.05A(3), prohibits Catoctin Power from causing or permitting the discharge of emissions from any fuel burning equipment, other than water in an uncombined form, which is greater than 20% opacity. c) COMAR 26.11.09.08G(2) Control of NOx Emissions for Major Stationary Sources, Requirements for Fuel-Burning Equipment with a Capacity Factor of 15 Percent or Less, and Combustion Turbines with a Capacity Factor Greater than 15 Percent—Limits Catoctin Power, as the owner/operator of a CT with a capacity factor greater than 15%, to an hourly average NOx emission rate of not more than 42 ppm when burning gas (dry volume at 15% oxygen) or to meeting applicable Prevention of Significant Deterioration limits, whichever is more restrictive. d) COMAR 26.11.09.08B(2) Control of NOx Emissions for Major Stationary Sources, Demonstration of Compliance—Requires Catoctin Power to demonstrate compliance with 26.11.09.08 as follows: i. For installations equipped with a continuous emissions monitor (CEM), compliance with the NOx emissions standards in this regulation shall be established using CEM data; or ii. For all other installations, compliance with the NOx emissions standards in this regulation shall be established by stack tests using Method 7 of the test methods referenced in COMAR 26.11.01.04C(1) or other test methods approved by ARMA and the EPA. e) COMAR 26.11.17.03B(2) Requirements for Major New Sources and Modifications, General Conditions—Requires Catoctin Power to meet an emission limitation which specifies the lowest achievable emission rate for the source for emissions of NOx and VOCs. f) COMAR 26.11.29 and .30 NOx Reduction and Trading Program—Requires Catoctin Power to hold an allowance for each ton of NOx emissions from the combustion turbines by the reconciliation date of November 30 of each calendar year.
|
No change. |
|
Agreed |
|
PPRP-14 P |
The combustion turbines are subject to NSPS 40 CFR 60, Subpart GG – Standards of Performance for Stationary Gas Turbines, and related provisions of 40 CFR §60.7 and §60.8, which contain various requirements for emission limitations, monitoring, testing, recordkeeping, and reporting, including but not limited to the following: a) Standard for NOx (40 CFR 60.332(a)(1))— On and after the date on which the performance test required by 40 CFR §60.8 is completed, Catoctin Power shall not cause to be discharged into the atmosphere any gases that contain NOx in excess of 75 ppmvd at 15% oxygen on a 1-hr average basis. b) Standard for SO2 (40 CFR 60.333(b))— On and after the date on which the performance test required by 40 CFR §60.8 is completed, Catoctin Power shall not burn any fuel which contains total sulfur in excess of 0.8 percent by weight.
c)
Monitoring of Operations (40 CFR 60.334(e)-(f))—Catoctin Power: i. May elect to use a NOx CEMS installed, certified, operated, maintained, and quality-assured as described 40 CFR Section 60.334(b);
ii. May instead perform acceptable
continuous parameter monitoring described in 40 CFR Section 334(f):
B. For any turbine that
uses SCR to reduce NOx emissions, Catoctin Power shall
continuously monitor appropriate parameters to verify the proper
operation of the emission controls. d) Monitoring of Operations (40 CFR 60.334((g)) i. The parameters that are continuously monitored as described in paragraphs (a), (d), or (f) of 40 CFR §60.334 shall be monitored during the performance test required under §60.8, to establish acceptable values and ranges. Catoctin Power may supplement the performance test data with engineering analyses, design specifications, manufacturer's recommendations and other relevant information to define the acceptable parametric ranges more precisely. ii. Catoctin Power shall develop and keep on-site a parameter monitoring plan which explains the procedures used to document proper operation of the NOx emission controls. The plan shall include the parameter(s) monitored and the acceptable range(s) of the parameter(s) as well as the basis for designating the parameter(s) and acceptable range(s). Any supplemental data that Catoctin Power believes is necessary to clarify or support the plan, such as engineering analyses, design specifications, manufacturer's recommendations and other relevant information shall be included in the plan. iii. If Catoctin Power uses the low mass emissions methodology in 40 CFR 75.19 or the NOx emission measurement methodology in Appendix E to 40 CFR Part 75, the company may meet the requirements of this paragraph by developing and keeping on-site (or at a central location for unmanned facilities) a quality-assurance plan, as described in 40 CFR §75.19 (e)(5) or in Section 2.3 of Appendix E and Section 1.3.6 of Appendix B to 40 CFR Part 75. e) Monitoring of Operations (40 CFR 60.334(h))—In lieu of monitoring the total sulfur content of the fuel being fired in the turbines, Catoctin Power shall demonstrate that the fuel meets the definition of natural gas in 40 CFR §60.331(u), as demonstrated by one of the methods specified in 40 CFR 60.334(h)(3)(i) or (ii). f) Monitoring of Operations (40 CFR 60.334(j))—Catoctin Power shall submit reports of excess emissions and monitor downtime in accordance with 40 CFR 60.7(c). Excess emissions shall be reported for all periods of unit operation, including startup, shutdown and malfunction. Periods of excess emissions and monitor downtime for the purposes of reports required by 40 CFR 60.7(c) are as outlined in 40 CFR 60.334(j)(1) for NOx and 40 CFR 60.334(j)(2) for SO2. All reports required under 40 CFR 60.7(c) shall be postmarked by the 30th day following the end of each calendar quarter. g) Test Methods and Procedures (40 CFR 60.335) i. Catoctin Power shall conduct performance tests according to applicable requirements in 40 CFR 60.335(a) and 60.335(b)(7); ii. Catoctin Power shall determine compliance with the NOx emissions limitation in Condition 14(a) according to applicable procedures in 40 CFR 60.335(b)(1)-(3). The 3-run performance test required by 40 CFR 60.8 must be performed within +5 percent at 30, 50, 75, and 90-to-100 percent of peak load or at four evenly-spaced load points in the normal operating range of the gas turbine, including the minimum point in the operating range and 90-to-100 percent of peak load, or at the highest achievable load point if 90-to-100 percent of peak load cannot be physically achieved in practice. |
No change. |
|
Agreed |
|
PPRP-15 P |
The duct burners associated with the Catoctin Power combustion turbines are subject to NSPS Subpart Da-Standards of Performance for Electric Utility Steam Generating Units for Which Construction is Commenced After September 18, 1978, and related provisions of 40 CFR §60.7 and §60.8, including, but not limited to the following: a) Standard for Particulate Matter (40 CFR 60.42a(a)(1))--On and after the date on which the performance test required to be conducted under 40 CFR §60.8 is completed, Catoctin Power shall not cause to be discharged into the atmosphere from any affected facility any gases which contain filterable particulate matter in excess of 13 ng/J (0.03 lb/million Btu) heat input. b) Standard for Particulate Matter (40 CFR 60.42a(b))—On and after the date the particulate matter performance test required to be conducted under 40 CFR §60.8 is completed, Catoctin Power shall not cause to be discharged into the atmosphere from any affected facility any gases which exhibit greater than 20% opacity (6-minute average), except for one 6-minute period per hour of not more than 27% opacity; c) Standard for SO2 (40 CFR 60.43a(b))—On and after the date the particulate matter performance test required to be conducted under 40 CFR §60.8 is completed, Catoctin Power shall not cause to be discharged into the atmosphere from any affected facility any gases which contain sulfur dioxide in excess of 86 ng/J (0.20 lb/million Btu) heat input; d) Standard for NOx (40 CFR 44a(d)(1))—On and after the date on which the initial performance test required to be conducted under 40 CFR §60.8 is completed, Catoctin Power shall not cause to be discharged into the atmosphere any gases which contain nitrogen oxides (expressed as NO2) in excess of 200 nanograms per joule (1.6 pounds per megawatt-hour) gross energy output, based on a 30-day rolling average, except as provided under 40 CFR §60.46a(k)(1), which states that compliance with this NOx standard for the duct burners used in combined cycle systems shall be determined by compliance with the following:
ii. Method 7E of 40 CFR Part 60 Appendix A shall be used to determine the NOx concentrations (Csg and Cte). Method 2, 2F or 2G of Appendix A of 40 CFR Part 60, as appropriate, shall be used to determine the volumetric flow rates (Qsg and Qte) of the exhaust gases. The volumetric flow rate measurements shall be taken at the same time as the concentration measurements. iii. Catoctin Power shall provide information satisfactory to the Administrator or demonstrate the average hourly gross energy output from the steam generating unit, and the average hourly percentage of the total heat input to the steam generating unit derived from the combustion of fuel in the affected duct burner. iv. Compliance with the emissions limits under 40 CFR §60.44a (d)(1) is determined by the three-run average (nominal 1-hour runs) for the initial and subsequent performance tests. e) Compliance Provisions (40 CFR 60.46a(a)-(c))—NOx, PM, and SO2 limits in this Subpart (herein Condition 15(a)-(d)) shall apply at all times, except during periods of startup, shutdown, or malfunction. f) Compliance Provisions (40 CFR 60.46a(e))—After the initial performance test required under §60.8, compliance with the SO2 emission limitations and percentage reduction requirements under §60.43a and the NOx emission limitations under §60.44a is based on the average emission rate for 30 successive boiler operating days. A separate performance test is completed at the end of each boiler operating day after the initial performance test, and a new 30 day average emission rate for both SO2 and NOx and a new percent reduction for SO2 are calculated to show compliance with the standards. g) Compliance Provisions (40 CFR 60.46a(f))— For the initial performance test required under §60.8, compliance with the SO2 emission limitations and percent reduction requirements under 40 CFR §60.43a and the NOx emission limitation under 40 CFR § 60.44a is based on the average emission rates for SO2, NOx, and percent reduction for SO2 for the first 30 successive boiler operating days. The initial performance test is the only test in which at least 30 days prior notice is required unless otherwise specified by the Administrator. The initial performance test is to be scheduled so that the first boiler operating day of the 30 successive boiler operating days is completed within 60 days after achieving the maximum production rate at which the affected facility will be operated, but not later than 180 days after initial startup of the facility. h) Compliance Provisions (40 CFR 60.46a(g))—Compliance is determined by calculating the arithmetic average of all hourly emission rates for SO2 and NOx for the 30 successive boiler operating days, except for data obtained during startup, shutdown, malfunction (NOx only), or emergency conditions (SO2 only). Compliance with the percentage reduction requirement for SO2 is determined based on the average inlet and average outlet SO2 emission rates for the 30 successive boiler operating days; i) Compliance Provisions (40 CFR 60.46a(i))—Catoctin Power shall calculate NOx emissions by multiplying the average hourly NOx output concentration, measured according to the provisions of 40 CFR §60.47a(c), by the average hourly flow rate, measured according to the provisions of 40 CFR §60.47a(l), and divided by the average hourly gross energy output, measured according to the provisions of 40 CFR §60.47a(k).
j)
Emissions Monitoring (40 CFR 60.47a(c)(1)-(2) and (d)-(f))—(1)
Catoctin Power shall install, calibrate, maintain, and operate a
continuous emissions monitoring system (CEMS), and record the output of
the system, for measuring NOx emissions discharged to the
atmosphere; or (2) if the owner or operator has installed a NOx
emission CEMS to meet the requirements of 40 CFR Part 75 and is
continuing to meet the ongoing requirements of 40 CFR Part 75, that CEMS
may be used to meet the requirements of this condition, except that the
owner or operator shall also meet the requirements of 40 CFR §60.49a.
Data reported to meet the requirements of 40 CFR § 60.49a shall not
include data substituted using the missing data procedures in subpart D
of part 75 of this chapter, nor shall the data have been bias adjusted
according to the procedures of 40 CFR Part 75. k) Compliance Provisions (40 CFR 60.48a(a)) which requires that in conducting the performance tests required in 40 CFR §60.8, Catoctin Power use as reference methods and procedures the methods in Appendix A of 40 CFR Part 60 or the methods and procedures as specified in 40 CFR 60.48a, except as provided in 40 CFR §60.8(b); Subpart Da 40 CFR 60.48a requires that Catoctin Power determine compliance with the particulate matter, SO2, and NOx standards through methods and procedures as spelled out in sections 40 CFR 60.48a(b), (c) and (d). l) Reporting Requirements (40 CFR 60.49a) requires Catoctin Power to submit to the Administrator the performance test data for SO2, NOx, and particulate matter emissions according to the specifications in 40 CFR 60.49a; and 40 CFR 60.49a(f) requires that, for any periods for which opacity, SOx or NOx emissions data are not available, Catoctin Power must submit a signed statement indicating if any changes were made in operation of the emission control system during the period of data unavailability. Operations of the control system and affected facility during periods of data unavailability are to be compared with operation of the control system and affected facility before and following the period of data unavailability. |
No change. |
|
Agreed |
|
PPRP-16 P |
The combustion turbines and associated duct burners and heat recovery steam generators are subject to all applicable permitting provisions of the Acid Rain program under 40 CFR Part 72, including, but not limited to: a) Subpart A 72.9(b)(1) requires Catoctin Power, to the extent applicable, to comply with monitoring requirements in 40 CFR Part 75; b) Subpart A 72.9(c) requires Catoctin Power to hold allowances in the unit’s compliance subaccount not less than the total annual emissions of SO2 for the previous year and comply with applicable Acid Rain limits for SO2; c) Subpart A 72.9(e) requires Catoctin Power to submit a proposed offset plan if emission limitations are exceeded; and d) Subpart A 72.9(f) requires Catoctin Power, unless otherwise provided, to retain required documents for a period of 5 years from the date that the document was created. Documents may include, but are not limited to, certificates of representation, emissions monitoring information, copies of reports, compliance certifications, and other documentation pertaining to the Acid Rain program. |
No change. |
|
Agreed |
|
PPRP-17 P |
The combustion turbines and associated duct burners and heat recovery steam generators are subject to all applicable monitoring provisions of the Acid Rain program under 40 CFR Part 75, including, but not limited to: a) Subpart A 75.4(b) which generally requires Catoctin Power, in accordance with 40 CFR 75.20, to ensure that all applicable monitoring systems for SO2, NOx, carbon dioxide (CO2), and volumetric flow required under 40 CFR Part 75 to be installed and all certification tests completed not later than 90 days after the date the unit commences commercial operation; b) Subpart B 75.10 which generally requires Catoctin Power to measure, as applicable, opacity, SO2, NOx, and CO2 emissions; and to ensure that continuous emission monitoring systems required by 40 CFR Part 75 meet the equipment, installation, and performance specifications in 40 CFR Part 75; and are maintained according to the quality assurance and quality control procedures in this part; c) Subpart F 75.53(a) which generally requires Catoctin Power to prepare a monitoring plan with sufficient information on applicable continuous opacity or emissions monitoring systems to demonstrate that all SO2, NOx, CO2 emissions and opacity, as required, are monitored and reported; d) Subpart F 75.57(a) which requires Catoctin Power to keep a file for each affected unit of all measurements, data, reports, and other information required by 40 CFR Part 75 in a form suitable for inspection for at least 3 years from the date of each record; e) Subpart F 75.57(b)-(f) which require Catoctin Power to record various operations, emissions, and other information, as specified; and f) Subpart G 75.60(a) and (b) which generally require Catoctin Power to comply with all reporting requirements, with all signatory requirements of §72.21 of this chapter for all submissions, and with all required certifications and reports. |
No change. |
|
Agreed |
|
PPRP-18 P |
The emergency diesel generator and the firewater pump engine at the Catoctin Power facility and the emergency diesel generator at the water supply pump house are each subject to all applicable federally enforceable State air quality requirements including, but not limited to, the following regulations:
a)
COMAR 26.11.09.05B(2)-(4) Visible Emissions Stationary Internal
Combustion Engine Powered Equipment—Prohibits Catoctin Power from
causing or permitting the discharge of emissions from any engine: b) COMAR 26.11.09.07A(1)(c) Control of Sulfur Oxides from Fuel Burning Equipment—Prohibits Catoctin Power from burning, selling, or making available for sale any fuel with a sulfur content by weight in excess of 0.3% for distillate fuel oils.
|
No change. |
|
Agreed |
|
PPRP-19 P |
The cooling tower at the Catoctin Power facility is subject to all applicable federally enforceable State air quality requirements including, but not limited to, the following regulations: a) COMAR 26.11.06.02C(1) Visible Emissions—Prohibits Catoctin Power from causing or permitting the discharge of emissions from any installation or building, other than water in an uncombined form, which is greater than 20% opacity. The visible emissions standards in §C of this regulation do not apply to emissions during startup and process modifications or adjustments, or occasional cleaning of control equipment, if: (a) the visible emissions are not greater than 40% opacity; and (b) the visible emissions do not occur for more than 6 consecutive minutes in any 60-minute period.
|
No change. |
|
Agreed |
|
PPRP-20 P |
Catoctin Power shall employ Best Available Control Technology (BACT) to control emissions of particulate matter (PM10), carbon monoxide (CO), sulfur dioxide (SO2), and nitrogen oxides (NOx) from the combustion turbines and associated duct burners and heat recovery steam generators.
[Table Not Inserted] |
* * * * |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power believes the paraphrasing proposed for the lead paragraph is confusing and subject to misinterpretation. For example, the paraphrasing could be interpreted to mean that Catoctin Power has an ongoing obligation to retrofit with best available control technology regardless of whether Catoctin Power has modified the facility. This interpretation is not consistent with the law.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN.
|
Agreed |
|
PPRP-21 P |
[Table Not Inserted] |
No change. |
|
Agreed |
|
PPRP-22 P |
[Table Not Inserted] |
No change. |
|
Agreed |
|
PPRP-23 |
Catoctin Power shall design the firewater pump engine to meet the following Best Available Control Technology (BACT) standards for particulate matter (PM10), carbon monoxide (CO), sulfur dioxide (SO2), and nitrogen oxides (NOx) from the firewater heater engine. Emissions shall be designed to achieve the emission limits:
[Table Not Inserted] |
No change. |
|
Agreed |
|
PPRP-24 |
Catoctin Power shall design the cooling tower to meet the following Best Available Control Technology (BACT) standards for particulate matter (PM10) from the cooling tower. Emissions shall be designed to achieve the following BACT emission limits:
[Table Not Inserted] |
No change. |
|
Agreed |
|
PPRP-25 |
Emissions from the combustion turbines and associated duct burners and heat recovery steam generators shall meet the following Lowest Achievable Emission Rate (LAER) standards, except during periods of startup, shutdown, and malfunction:
|
No change. |
|
Agreed |
|
PPRP-26 P |
Emissions from the emergency diesel generator at the Catoctin Power facility shall be designed to meet the following emission limits to meet Lowest Achievable Emission Rate (LAER) standards:
|
No change. |
|
Agreed |
|
PPRP-27 P |
Emissions from the emergency diesel generator at the water supply pump house shall be designed to meet the following emission limits to meet Lowest Achievable Emission Rate (LAER) standards:
|
No change. |
|
Agreed |
|
PPRP-28 P |
Emissions from the firewater pump engine shall be designed to meet the following emission limits to meet Lowest Achievable Emission Rate (LAER) standards:
|
No change. |
|
Agreed |
|
PPRP-29 P |
The combustion turbines and associated duct burners and heat recovery steam generators shall be limited to the following: a) Operation of each duct burner shall not exceed 577 million Btu per hour (MMBtu/hr, higher heating value) each, and 2,308,000 million Btu during any consecutive 12-month period. b) Each duct burner shall operate for no more than 4,000 hours during any consecutive 12-month period.
|
No change. |
|
Agreed |
|
PPRP-30 P |
Emissions from the combustion turbines and associated duct burners and heat recovery steam generators shall not exceed the following during any consecutive 12-month period, including emissions during periods of startup and shutdown:
[Table Not Inserted]
|
No change. |
|
Agreed |
|
PPRP-31 P |
Facility-wide emissions shall be limited to the following in any consecutive 12-month rolling period:
[Table Not Inserted]
|
No change. |
|
Agreed |
|
PPRP-32 P |
At least 30 days prior to conducting any compliance stack test, Catoctin Power shall submit a test protocol to ARMA for review and approval. a) Compliance stack testing shall be conducted in accordance with ARMA Technical Memorandum (TM) 91-01, "Test Methods and Equipment Specifications for Stationary Sources" (January 1991), as amended by Supplement 1 (1 July 1991), 40 CFR 51, 40 CFR 60, or subsequent test protocols approved by ARMA. b) Compliance testing for particulate matter emissions from the combustion turbines shall be conducted according to EPA Method 8 and EPA Method 202.
|
No change. |
|
Agreed |
|
PPRP-33 P |
Compliance stack testing of the combustion turbines shall be conducted within 180 days after initial startup to quantify pollutant emissions and demonstrate compliance with the emission limits specified in the CPCN for the following pollutants: NOx, SO2, PM10, and CO. |
No change. |
|
Agreed |
|
PPRP-34 P |
|
No change. |
|
Agreed |
|
PPRP-35 P |
Testing of the combustion turbines shall be performed when operating at a minimum of 90% of the design turbine load for compressor inlet conditions. If testing cannot be performed at the minimum turbine load, then the actual turbine load during testing shall become the allowable permitted turbine load. |
No change. |
|
Agreed |
|
PPRP-36 P |
Within 60 days after completing the initial stack tests, Catoctin Power shall provide ARMA copies of the testing results. |
No change. |
|
Agreed |
|
PPRP-37 P |
In accordance with COMAR 26.11.01.04A, Catoctin Power may be required by ARMA to conduct additional stack tests to determine compliance with COMAR Title 26, Subtitle 11. This testing will be done at a reasonable time. |
No change. |
|
Agreed |
|
PPRP-38 P |
Final results of each compliance stack test must be submitted to ARMA within 60 days after completion of the test. Analytical data shall be submitted to ARMA directly from the emission testing company. |
No change. |
|
Agreed |
|
PPRP-39 P |
Catoctin Power shall furnish written notification to ARMA and EPA of the following events:
|
No change. |
|
Agreed |
|
PPRP-40 P |
Catoctin Power shall certify the actual emissions of regulated pollutants from the facility.
|
No change. |
|
Agreed |
|
PPRP-41 P |
All records and logs required by this CPCN shall be maintained at the facility for at least 5 years after the completion of the calendar year in which they were collected. These data shall be readily available for inspection by representatives of ARMA. |
No change. |
|
Agreed |
|
PPRP-42 P |
All air quality notifications and reports required by this CPCN shall be submitted to:
Administrator, Compliance Program Air and Radiation Management Administration 1800 Washington Boulevard
|
No change. |
|
Agreed |
|
PPRP-43 |
All notifications and reports required by 40 CFR 60 and Subpart GG, Subpart Da, and the Acid Rain provisions, unless specified otherwise, shall be submitted to: Regional Administrator, US Environmental Protection Agency Region III 1650 Arch Street
|
No change. |
|
Agreed |
|
PPRP-44 P |
|
No change. |
|
Agreed |
|
PPRP-45 P |
|
* * * *
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned with the language proposed in subsection d). Catoctin Power has requested authorization to use Potomac River water for both wet cooling of steam condensers and fire suppression. Catoctin Power has clarified this in a letter to PPRP.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-46 P |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power does not support the language included in the second sentence. Catoctin Power’s understanding from PPRP is that the second sentence is intended to paraphrase Maryland Environment Code Section 5-510. However, Catoctin Power does not believe the proposed paraphrasing is an accurate reflection of the law. Therefore, Catoctin Power has drafted the Proposed Final Condition, which uses the specific language found in Section 5-510.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
PPRP-47 P |
|
No change. |
|
Agreed |
|
PPRP-48 P |
|
No change. |
|
Agreed |
|
PPRP-49 P |
|
|
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-50 P |
|
No change. |
|
Agreed |
|
PPRP-51 P |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power would like to make clear that it is violations by Catoctin Power, as opposed to violations by third parties, that may result in suspension or revocation of the appropriation.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-52 P |
|
No change. |
|
Agreed |
|
PPRP-53 P |
|
No change. |
|
Agreed |
|
PPRP-54 P |
Catoctin Power shall conduct the following monitoring activities in support of the surface water appropriation:
|
No change. |
|
Agreed |
|
PPRP-55 P |
Prior to construction, but not longer than 24 months following issuance of the CPCN, Catoctin Power shall provide to PPRP and the PSC for review and approval final design documentation, including, but not limited to, drawings, materials and equipment specifications, and Standard Operating Procedures (SOPs) related to the proposed means to chlorinate the reclaimed water and maintain the residual chlorine levels for a minimum of six hours prior to the time that the reclaimed water is used in the power plant’s cooling water makeup system, water quality monitoring systems, raw water storage, and proposed measures to appropriately manage the delivery of reclaimed water of an unacceptable quality due to an upset condition at the Ballenger Creek Wastewater Treatment Plant (WWTP) or the planned McKinney WWTP, as detailed in Conditions 56 through 58. |
No change. |
|
Agreed |
|
PPRP-56 P |
Catoctin Power shall chlorinate the effluent obtained from the Ballenger Creek WWTP or the planned McKinney WWTP source to sufficiently establish and maintain detectable free chlorine residual in the reclaimed water for a minimum of six hours prior to the time that the reclaimed water is used in the power plant’s cooling water makeup system. Catoctin Power shall have the ability to add additional chlorine, if necessary, to reestablish the free chlorine residual for reclaimed water stored on site. |
No change. |
|
Agreed |
|
PPRP-57 P |
Following receipt of reclaimed water from the County WWTP(s) and prior to entry in the on-site water storage tank, Catoctin Power shall as a minimum perform daily sampling and analyses for total suspended solids, pH, turbidity, fecal coliform, and free chlorine residual. These tests shall be performed in accordance with procedures specified in 40 CFR 136, and the results maintained in the facility’s operating log. Turbidity values greater than 5 Nephelometric Turbidity Units (NTU) shall result in effluent water unsuitable for use in the cooling water system. Catoctin Power shall submit these analytical data to PPRP for interagency review once per quarter. |
No change. |
|
Agreed |
|
PPRP-58 |
Whenever exceedances of the 5 NTU threshold occur following the receipt of reclaimed water from the County WWTP (see Condition No. 57 for monitoring requirements), the following procedures shall apply:
|
No change. |
|
Agreed |
|
PPRP-59 |
Where Catoctin Power uses reclaimed water in place of potable water, consistent with specifications outlined by the American Water Works Association (AWWA) in “Guidelines for Distribution of Nonpotable Water,” to prevent inadvertent and inappropriate use of the WWTP reclaimed water, Catoctin Power shall ensure the following:
|
No change. |
|
Agreed |
|
PPRP-60 |
Catoctin Power shall conduct the following monitoring activities in support of the use of reclaimed water and compliance with consumptive use requirements:
|
No change. |
|
Agreed |
|
PPRP-61 |
|
No change. |
|
Agreed |
|
PPRP-62 |
Low Flow Augmentation.
|
Low Flow Augmentation.
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the language is confusing and subject to misinterpretation.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-63 |
If Catoctin Power elects to use the Millville Quarry as a source of low flow augmentation storage, Catoctin Power shall conduct a baseline study of the daily fluctuation of water levels in the Millville Quarry for the period spanning at least June 1 through December 31 to demonstrate the ability to accurately measure drawdown in the quarry. The study shall include, but not be limited to the following:
Catoctin Power shall provide a plan of study to MDE Water Management Administration for review and approval, and to PPRP for review, two months prior to the planned implementation of the study. The results of the study shall be used to develop the Standard Operating Procedures (SOPs) required under Condition 65, and shall be provided to MDE Water Management Administration and PPRP for review, concurrent with the SOPs.
|
Catoctin Power shall provide a plan of study to MDE Water Management Administration for review and approval, and to PPRP for review, two months prior to the planned implementation of the study. The results of the study shall be used to develop the Standard Operating Procedures (SOPs) required under Condition 65, and shall be provided to MDE Water Management Administration and PPRP for review, concurrent with the SOPs. |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power has certain concerns regarding PPRP’s proposed language. These concerns are discussed in Mr. Gregory Powell’s rebuttal testimony.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-64 |
|
|
Catoctin Power does not support the Draft Condition Currently In The Record. Please see Mr. Gregory Powell’s rebuttal testimony for a discussion of Catoctin Power’s concerns.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN.
|
Pending |
|
PPRP-65 |
|
Catoctin Power shall
develop SOPs to accurately measure |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, this condition only applies if Catoctin Power elects to use the Millville Quarry for purposes of low flow augmentation. If Catoctin Power does not elect to use the Millville Quarry, or if Catoctin Power elects to curtail in lieu of providing augmentation water, this condition should not apply. For these reasons, the submittal and approval dates for the SOPs should be linked to Catoctin Power’s use of the Millville Quarry for low flow augmentation purposes. In addition to resolving Catoctin Power’s concern regarding the submittal date, the Proposed Final Condition clarifies certain language.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-66 |
If Catoctin Power elects to use the Old Standard Quarry as a source of low flow augmentation storage, Catoctin Power shall submit to MDE Water Management Administration and PPRP results of any available analyses conducted by Old Standard Quarry to assess the potential presence of tetrachloroethylene (PCE) in the water. If these analyses are not sufficient to demonstrate whether or not the presence of PCE will adversely affect the use of the quarry for low flow augmentation, Catoctin Power shall conduct or cause a third party to conduct a study of the water quality in the Old Standard Quarry to ensure that the potential presence of PCE in the water will not adversely affect the use of the quarry for low flow augmentation. Catoctin Power shall provide a plan of study to MDE Water Management Administration for review and approval, and PPRP for review, two months prior to the planned implementation of the study. Any study conducted by Catoctin Power shall include the collection and analysis of multiple samples distributed across the quarry and at depth to determine the presence or absence and distribution of PCE in the water. Catoctin Power shall complete the study within six months of the issuance of the CPCN, and provide the results of the study to MDE Water Management Administration for review and approval, and PPRP for review within two months of completing the study. |
|
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-67 |
Unless adjusted based on the development of the Standard Operating Procedures described in Condition 65, Catoctin Power shall determine the quantity of augmentation water released each day by calculating the difference in volume in the quarry from which Catoctin releases the augmentation water at the start of the augmentation day and the volume in the quarry at the end of the augmentation day (i.e., 24 hours after augmentation begins). Flow measurements using a totalizing flow meter or pump curves shall be used as secondary information to determine the amount of water released from storage each day. Consideration of rainfall, rainfall entering the quarry, and evaporation will be made using the following methods:
|
No change. |
|
Agreed |
|
PPRP-68 |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, PPRP’s proposed conditions give Catoctin Power the right to use either the Millville quarry, the Old Standard quarry, or both of them. Catoctin Power should only be required to provide an affidavit for the quarry or quarries it elects to use. Moreover, PPRP’s proposed conditions give Catoctin Power the option to either augment the River or curtail. Consequently, Catoctin Power believes it is more appropriate to link the affidavit’s submittal date to Catoctin Power’s use of the quarry than to link it to the use of water and operation of the plant. Catoctin Power also has other minor clarifications with regard to the proposed language.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-69 |
Catoctin Power shall secure all necessary permits and approvals that are required under federal, state or local laws and regulations to satisfy Catoctin’s obligations under COMAR 26.17.07, and provide MDE Water Management Administration copies of all necessary permits and approvals, within at least one month in advance of initiation of withdrawal from the Potomac River or use of reclaimed water from Frederick County to ensure that the quarry water can be released from storage when required under Condition 62. |
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, PPRP’s proposed conditions give Catoctin Power the option to either augment the River or curtail. Consequently, Catoctin Power believes it is more appropriate to link the demonstration date to Catoctin Power’s use of the quarry for augmentation than to link it to the use of water and operation of the plant.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-70 |
|
|
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
PPRP-71 |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the language is confusing and subject to misinterpretation.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-72 |
|
No change. |
|
Agreed |
|
PPRP-73 |
As directed by MDE Water Management Administration, Catoctin Power shall prepare a Stormwater Pollution Prevention Plan, incorporating best management practices to prevent runoff of contaminated stormwater. |
No change. |
|
Agreed |
|
PPRP-74 |
|
No change. |
|
Agreed |
|
PPRP-75 |
|
No change. |
|
Agreed |
|
PPRP-76 |
This CPCN applies to the transmission line interconnection and pipeline linear facilities (including natural gas and water pipelines) as presented in Catoctin Power’s application (including amendments and supplements) and direct testimony in this proceeding. If any other configuration for transmission interconnection or natural gas pipeline linear facilities is proposed, including collocating a new transmission line along an existing right-of-way, an amended CPCN will be required. |
No change. |
|
Agreed |
|
PPRP-77 |
Catoctin Power shall provide to PPRP and PSC detailed plans regarding the routes for water supply and effluent pipelines prior to construction but no later than 3 months after the NPS issues a right-of-way permit. The notification shall include plans showing the routes, and procedures for the installation of the pipelines. |
No change. |
|
Agreed |
|
PPRP-78 |
Catoctin Power shall provide as-built details on the following to PPRP and PSC in accordance with COMAR 20.80.04: engineering and construction plans of any transmission facilities and pipeline linear facilities, including dimensions and location of on-site transformers and switchgear; rights-of-way width; length and total acreage of the rights-of-way; transmission line structure and foundation types, dimensions and locations; transmission line conductor configuration; nominal length of span between transmission line structure; and jurisdictional wetlands boundaries within the rights-of way. |
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power notes that it will not be constructing transmission line structures. Therefore, Catoctin Power believes it may be appropriate to delete references to transmission line structures.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-79 |
Catoctin Power shall reduce tree clearing or trimming within the transmission line and pipeline linear facilities rights-of-way, to the extent practicable when constructing and maintaining the transmission line and pipeline linear facilities. In agricultural areas, grasses will be planted along streams where acceptable to the property owners. If the agricultural areas along streams are wetlands or wetland buffers, only grasses listed in Condition No. 75 shall be used. If agricultural areas along streams are uplands, the following grass species may be used: blue joint grass (Calamagrostis canadensis), switchgrass (Panicumvirgatum), little bluestem (Schizachyrium scoparium), or indian grass (Sorghastrum nutans). |
Catoctin Power shall reduce tree clearing or trimming within the transmission line and pipeline linear facilities rights-of-way, to the extent practicable when constructing and maintaining the transmission line and pipeline linear facilities. In agricultural areas, grasses will be planted in areas disturbed during construction along streams where acceptable to the property owners. If the agricultural areas along streams are wetlands or wetland buffers, only grasses listed in Condition No. 75 shall be used. If agricultural areas along streams are uplands, the following grass species may be used: blue joint grass (Calamagrostis canadensis), switchgrass (Panicumvirgatum), little bluestem (Schizachyrium scoparium), or indian grass (Sorghastrum nutans). |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the condition could be misinterpreted.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-80 |
Catoctin Power shall advise the PSC and PPRP that copies of contract specifications for clearing, construction, and rehabilitation of the rights-of-way are available sixty (60) days prior to the beginning of construction. Catoctin Power shall provide the same advisement to the PSC and PPRP for contract specifications for maintenance when made available to bidders. During any clearing of the right-of-way, Catoctin Power and its contractors shall leave tree roots and stumps in place, except where such roots and stumps interfere with structure locations, access roads, or other components of the transmission line or pipeline linear facilities. Cleared trees will be cut and windrowed along the edge of the right-of-way for wildlife habitat where acceptable to the property owner. Brush may be shredded and distributed on the cleared right-of-way as a ground cover to stabilize the soil surface. |
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power does not believe windrowing is appropriate in all areas. Additionally, Catoctin Power believes it would be appropriate to provide the requested information thirty (30) days prior to construction.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-81 |
If Catoctin Power selects a water supply that places a pump house and other appurtenances on the property of the C&O National Historical Park, Catoctin Power shall obtain an easement or right-of-way from the National Park Service, in accordance with the requirements of the National Park Service, to obtain an easement or right-of-way to access the Potomac River for the purpose of constructing a water intake structure and pipeline to withdraw water, a wastewater effluent pipeline and diffuser to discharge wastewater, and any other ancillary facilities. |
|
|
|
|
PPRP-82 |
If Catoctin Power selects Water Supply Option B and determines the need to place a pump house and other appurtenances on the property of the State Highway Administration in the US Route 15 corridor underneath or adjacent to the Route 15 bridge, Catoctin Power shall address environmental and socioeconomic impacts to the C&O Canal National Historical Park, in accordance with the requirements of applicable federal, state and local laws. |
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power notes that PPRP’s proposed CPCN conditions do not define “Option B” and that referencing “Option B” is unnecessary to achieve this condition’s objectives.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-83 |
If Catoctin Power constructs a pipeline along US 15 between the Potomac River and US 340 (Route B), Catoctin Power shall enter into an agreement via a Memorandum of Understanding (MOU) or a Letter of Agreement (LOA) with the State Highway Administration (SHA). The MOU or LOA shall state that Catoctin Power will be financially responsible for the relocation of the pipeline if any future improvements to US 15 are required. |
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power notes that PPRP’s proposed CPCN conditions do not define “Option B” and that referencing “Option B” is unnecessary to achieve this condition’s objectives.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-84 |
|
No change. |
|
Agreed |
|
PPRP-85 |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the proposed language is confusing and could be misinterpreted.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-86 |
Catoctin Power shall develop a detailed visual impact mitigation and landscaping plan for all above ground facilities associated with the water supply and discharge pipelines and submit it to PPRP and the PSC for review and approval prior to commencing construction of the facility. The plan shall address, at a minimum, specific steps that will be taken to minimize visual impact of above-ground facilities on the Chesapeake and Ohio (C&O) Canal National Historical Park and on the Potomac River. |
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the proposed language is confusing and could be misinterpreted.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-87 |
Catoctin Power shall work closely with DNR Division of Forestry, Frederick County, and PPRP to prepare a forest planting plan to 1) partially mitigate for incremental nitrogen deposition from the Catoctin facility and, 2) mitigate forest losses associated with the construction of linear facilities. For mitigation of nitrogen deposition, Catoctin Power shall prepare a plan detailing methods and specifications for establishment of a total of 19 acres of forest. While on-site forest planting is preferred, off-site reforestation is acceptable, but areas must be identified as appropriate by tools developed by DNR to evaluate the suitability of riparian buffer planting and extensions of the green infrastructure (important natural habitat areas). Locations within Frederick County, especially those within close proximity to the project site should be prioritized. In addition, Catoctin Power shall replace the trees removed for construction of the linear facilities related to the project by assuming that at least one additional acre shall be planted for each acre of forest removed during construction. The plan shall provide details on why selected sites are most appropriate for mitigation and establishment of forest resources. At a minimum, planting plans, specifications, and monitoring schedules for all sites shall be included in the plan. A draft forest planting plan shall be submitted to DNR Division of Forestry and PPRP within six months of issuance of this CPCN. |
|
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-88 |
Catoctin Power shall submit to Maryland Historical Trust (MHT) a copy of training programs, or guidelines provided to inspectors or contractors, to identify and/or protect unforeseen archeological sites that may be revealed during construction of the power plant and associated facilities. If such archeological sites or relics are identified in the project area, Catoctin Power, in consultation with and as approved by MHT, shall develop and implement a plan for avoidance and protection, data recovery, or destruction without recovery of the properties adversely affected by the project. |
No change. |
|
Agreed |
|
PPRP-89 |
|
No change. |
|
Agreed |
|
PPRP-90 |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the condition is confusing and could be misinterpreted.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-91 |
|
|
Catoctin Power does not support the Draft Condition Currently In The Record. Catoctin Power agrees to require trucks delivering aqueous ammonia to the Catoctin Power facility to use designated truck routes. However, for the reasons provided in Mr. Richard Zwolak’s rebuttal testimony, Catoctin Power does not believe designated truck routes are appropriate for other large trucks.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
PPRP-92 |
|
No change. |
|
Agreed |
|
PPRP-93 |
|
No change. |
|
Agreed |
|
PPRP-94 |
|
No change. |
|
Agreed |
|
PPRP-95 |
Catoctin Power shall conduct a Traffic Impact Study (TIS) for its heavy truck usage during construction. The study shall consider impacts to State roads that will carry heavy truck traffic to the construction site, including I-270, MD 85 and US 15. |
No change. |
|
Agreed |
|
PPRP-96 |
|
|
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-97 |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power is concerned that the proposed language could be misinterpreted. Moreover, because plant construction typically commences long before final lighting design is conducted, Catoctin Power believes it is more appropriate to link the lighting plan’s submittal date to facility operation rather than to facility construction.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-98 |
|
|
Catoctin Power generally supports the Draft Condition Currently In The Record. However, Catoctin Power notes that, due to the PSC’s preemption authority over Frederick County, Frederick County reviewed and accepted, but did not officially “approve,” Catoctin Power’s proposed Site Plan.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Agreed |
|
PPRP-99 |
Catoctin Power shall provide to PPRP and the PSC copies of its security procedures, in particular those procedures addressing site and plant safety and security during construction and operation of the power plant. The procedures should address issues such as how Catoctin Power plans to control vehicle and construction worker access and protect any vulnerable assets from being threatened from outside the perimeter of the property. The procedures should also identify how local, state, and federal agencies would be coordinated in the event of a large-scale emergency. Security procedures should consider the effects of any proposed measures on the surrounding community and mitigate adverse effects to the maximum extent possible. |
No change. |
|
Agreed |
|
PPRP-100 |
|
No change. |
|
Agreed |
|
PPRP-101 |
Catoctin Power shall conduct a detailed assessment of the emergency response capabilities of the Carroll Manor Volunteer Fire Company. Should additional or special equipment be required to provide adequate emergency services for the power plant, Catoctin Power shall reimburse the Carroll Manor Volunteer Fire Company or the appropriate agency for these expenses as long as they related to the need to provide adequate emergency services for the power plant. |
No change. |
|
Agreed |
|
PPRP-102 |
During the construction of the Catoctin facility, Catoctin Power or its contractors shall provide written notification to nearby residents of the expected schedule for steam venting activities that could produce high-intensity noise incidents. This advance notification must be provided at least 24 hours before steam venting begins, and must be distributed to residents living within 1 mile of the point where the steam venting will occur. |
No change. |
|
Agreed |
|
PPRP-103 |
|
No change. |
|
Agreed |
|
PPRP-104 |
Catoctin Power shall confirm noise levels at the boundaries of the facility, after the plant is operational, to verify results of the predictive analysis. The scope of work for the noise study shall be provided to MDE's Noise Control Program for review and approval within ninety (90) days prior to anticipated commercial operation. The noise study shall include monitoring at Eastalco property boundaries near residential properties. Measurements will be taken while the plant is operating at full load, to represent maximum noise emissions. Results of the noise study shall be provided to the PSC, PPRP and MDE’s Noise Control Program within six months after a) the Catoctin Power facility begins commercial operation, or b) MDE’s Noise Control Program approves Catoctin Power’s proposed scope of work for the noise study, whichever is later. |
No change. |
|
Agreed |
|
PPRP-105 |
If the results of the post-construction noise study indicate that the operation of the facility is creating an exceedance of the Maryland noise standards or Frederick County zoning ordinance, Catoctin Power shall take corrective action in consultation with MDE's Noise Control Program. |
No change. |
|
Agreed |
|
PPRP-106 |
At least 2 months prior to construction, Catoctin Power shall provide to PPRP and PSC a Phase I Environmental Site Assessment (ESA), dated no earlier than two calendar years prior to the date of construction, and a Health and Safety Plan for the construction phase of the project. The Phase I ESA shall be conducted in conformance with the minimum requirements of ASTM Standard E 1527-00, “Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process”. The Health and Safety Plan shall comply with appropriate Occupational Safety and Health Administration (OSHA) guidelines to ensure worker protection during construction of the facility. |
No change. |
|
Agreed |
|
PPRP-107 |
Power Plant Assessment Division Department of Natural Resources Tawes State Office Building, B-3 580 Taylor Avenue
|
No change. |
|
Agreed |
|
PSC Staff Conditions |
||||
|
PSC-1 |
Catoctin Power shall file with the Public Service Commission a listing of the transmission system improvements required by PJM and certification that the improvements have been completed. |
No change. |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, the Transmission Owner may undertake most, if not all, of the system upgrades and the direct interconnection facilities construction. In this event, Catoctin Power will not be able to provide a direct 'certification' with respect to facilities that Catoctin Power is not responsible for constructing, even though such construction is funded by the project. Catoctin Power’s understanding based on Mr. Taborsky’s verbal testimony on December 9, 2004 is that a letter from Catoctin Power enclosing written correspondence from the party that conducts the construction will satisfy this proposed condition’s certification requirement. If this understanding is correct, Catoctin Power fully supports the Draft Condition Currently In The Record, and respectfully requests that the PSC include the Draft Condition Currently In The Record in any CPCN. |
Agreed |
|
PSC-2 |
Catoctin Power shall file with the Public Service Commission a listing of the interconnecting transmission line owner and certification that the interconnection requirements have been met. |
No change. |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, the Transmission Owner may undertake most, if not all, of the system upgrades and the direct interconnection facilities construction. In this event, Catoctin Power will not be able to provide a direct 'certification' with respect to facilities that Catoctin Power is not responsible for constructing, even though such construction is funded by the project. Catoctin Power’s understanding based on Mr. Taborsky’s verbal testimony on December 9, 2004 is that a letter from Catoctin Power enclosing written correspondence from the party that conducts the construction will satisfy this proposed condition’s certification requirement. If this understanding is correct, Catoctin Power fully supports the Draft Condition Currently In The Record, and respectfully requests that the PSC include the Draft Condition Currently In The Record in any CPCN. |
Agreed |
|
PSC-3 |
At the December 9, 2004 hearing, Mr. Taborsky requested that the PSC add a condition requiring Catoctin Power to file with the Commission a copy of its Interconnection Service Agreement. |
Within thirty (30) days after putting the project into service, Catoctin Power shall file with the Commission a copy of its Interconnection Service Agreement. |
The PSC staff did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN.
|
Agreed |
|
Frederick County |
||||
|
FC-1 |
The CPCN should reflect that its issuance does not require Frederick County to provide or sell effluent or potable water. |
The terms of this CPCN shall not be interpreted to require Frederick County to sell effluent or potable water to Catoctin Power. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-2 |
We believe that, at a minimum, the MDE will (and should) require that Sempra obtain a separate NPDES user discharge permit if there is to be a return flow through the County’s effluent outfall system. |
Catoctin Power shall obtain a separate NPDES user discharge permit prior to discharging wastewater through Frederick County’s effluent outfall system. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-3 |
If Frederick County agrees to sell effluent or potable water to Catoctin Power, Catoctin Power shall comply with and fulfill such requirements as the County might have regarding the use of effluent and those other terms and conditions that the BOCC might believe appropriate. |
Catoctin Power shall comply with all applicable local laws in connection with any purchase by Catoctin Power of effluent or potable water from Frederick County. |
Catoctin Power does not support the Draft Condition Currently In The Record. Any agreement between Frederick County and Catoctin Power for the purchase of effluent or potable water will occur pursuant to an arms length negotiation and agreement between Frederick County and Catoctin Power. While Catoctin Power agrees to comply with all applicable Frederick County laws in connection with any such purchase, it is inappropriate for the CPCN to require Catoctin Power to accept any terms or conditions that the County may request, as such requirement would undermine the parties’ ability to negotiate a purchase and sale agreement. On December 9, 2004, Mr. Marschner suggested that the County’s intent in proposing the Draft Condition Currently In The Record was to ensure that Catoctin Power must comply with all applicable County laws in connection with any purchase of effluent or potable water from the County. The Proposed Final Condition addresses this County request.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-4 |
Any special effluent water quality requirements that may be placed on the use of effluent water shall be based on sound technologically feasible methods of determining the “real time” quality of the effluent water and such methods shall be first validated based on the actual water quality leaving the County’s wastewater treatment facility. Any such limits shall be placed on Catoctin Power’s use of the water and not apply to the County or the County’s NPDES permit. |
None. |
Catoctin Power does not support the Draft Condition Currently In The Record. The condition raises commercial terms that are inappropriate for inclusion in the CPCN and are more appropriately addressed by Catoctin Power and Frederick County pursuant to an arms length negotiation for the purchase of effluent or potable water. Please see the rebuttal testimonies of Mr. Brent Waters and Mr. Gordon Chirdon for additional support for Catoctin Power’s opposition to this condition.
Catoctin Power does not support inclusion of any condition in the CPCN. |
Pending |
|
FC-5 |
If Catoctin Power uses effluent from Frederick County, concentration based limits may need to be imposed on Catoctin Power’s return flow to the Potomac River through the County’s system to preserve the quality of the effluent for use by others. |
None. |
Catoctin Power does not support the Draft Condition Currently In The Record. The proposed condition raises commercial terms that are inappropriate for inclusion in the CPCN and are more appropriately addressed by Catoctin Power and Frederick County pursuant to an arms length negotiation for the purchase of effluent or potable water. Please see the rebuttal testimonies of Mr. Brent Waters and Mr. Gordon Chirdon for additional support for Catoctin Power’s opposition to this condition.
Catoctin Power does not support inclusion of any condition in the CPCN. |
Pending |
|
FC-6 |
Catoctin Power shall work with EastAlco Aluminum to identify and place approximately 250 acres of land into permanent agricultural preservation. If at all possible, this property shall consist of the following: (1) account identifier – district 23, account number 437457, tax map 94, grid 3, parcel 76 – 144 acres west of Ballenger Creek Pike adjacent to St. Matthew’s Church that is owned by EastAlco; and (2) account identifier – district 01, account number 005391, tax map 94, grid 4, parcel 3 – 169.17 acres located on the east side of Ballenger Creek Pike, also owned by EastAlco, and located directly across the road from St. Matthew’s church and which wraps around the church cemetery. If the identified properties cannot be obtained for preservation, Catoctin Power shall work with EastAlco to identify other properties that would accomplish the BOCC’s intent of placing land into permanent agricultural preservation in order to act as a buffer between the Catoctin Power plant and the community, including St. Matthew’s church. If Catoctin Power is not able to obtain and place this land into permanent agricultural preservation by working with EastAlco, Catoctin Power shall work with the Carollton Manor Land Trust to identify and obtain 250 acres of land to be preserved for this purpose at Catoctin Power’s expense. |
None. |
Catoctin Power does not support the Draft Condition Currently In The Record. The County has not provided any evidence to suggest that Catoctin Power’s proposed buffering, as set forth in the County-approved Site Plan, is inadequate. Moreover, the County has not provided any evidence to suggest that the condition enhances buffering. Please see the rebuttal testimonies of Gordon Chirdon and Richard Zwolak for a detailed discussion of Catoctin Power’s opposition.
Catoctin Power does not support inclusion of any condition in the CPCN. |
Pending |
|
FC-7 |
We believe that any dead or missing trees along Manor Woods Road should be replaced and maintained as living trees. |
Dead trees or trees which have been cut down along the frontage of the Eastalco facility on Manor Woods Road shall be replaced by Catoctin when Catoctin does its tree planting. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-8 |
We believe that the proposed project’s structures should be earth tone colors to blend with the surrounding areas. |
Colors of major structures and buildings shall be earth tones. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-9 |
While perhaps simply restating a requirement already found in law, we believe that Sempra should work with the Maryland Department of the Environment to mitigate any wetland disturbances. |
Catoctin Power shall work with MDE to mitigate wetland disturbances as required under applicable federal, state and local laws. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-10 |
The Site Plan should be a condition to the CPCN.
|
The Site Plan drawings (Cover Sheet 1, Revision 0 dated 6/24/04; Site Plan Sheet 2, Revision 2 dated 8/9/04; Preliminary Stormwater Management Site Plan Sheet 3, Revision 0 dated 6/16/04; Sediment and Erosion Control site Plan Sheet 4, Revision 0 dated 6/16/04), attached herein, are deemed to meet Frederick County zoning requirements and the Project shall be designed and constructed in substantial conformity with these documents, provided that Frederick County Division of Permitting and Development Review (“DPDR”) shall have authority to approve any substantive changes that Catoctin may request to the design shown on the Site Plan drawings if DPDR verifies that such substantive changes comply with Frederick County zoning requirements. Regardless of the DPDR’s authority to approve such substantive changes, the PSC retains final override authority to approve Catoctin Power’s request for substantive changes. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-11 |
Catoctin should obtain general building, electric, plumbing and fire protection permits from Frederick County. |
The Project shall comply with applicable local building code requirements for structures, electrical systems, plumbing, and fire protection systems. For purposes of this condition, DPDR shall have responsibility for verifying that the Project complies with the above applicable local building code requirements and shall accommodate incremental execution of design and construction activities, provided however, that the PSC retains final override authority to verify compliance if DPDR unreasonably conditions or delays its verification. To support DPDR compliance verification activities, Catoctin shall (a) develop a schedule for document submittals and provide this schedule to DPDR, including regular schedule updates; (b) submit design drawings to DPDR for compliance verification at least 30 days (or lesser number of days mutually agreed to by Catoctin and DPDR) prior to the start of incremental construction covered by such design drawings; and (c) pay fees to DPDR equivalent to fees normally assessed by DPDR for analogous building permit verification activities. |
Catoctin Power generally supports the Draft Condition Currently In The Record. However, our understanding is that the CPCN process preempts local requirements that would otherwise apply to construction of a facility in Frederick County. With this understanding, Catoctin Power agrees to a condition that would provide the Frederick County DPDR with the right to review applicable portions of the design and construction of the facility for verification of compliance with local building codes.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-12 |
Catoctin Power shall comply with the site plan suggestions set forth in Bruce Dell’s September 16, 2003 memo under Site Improvement Plans section (pages 1 and 2) (in this memo “SWM” refers to storm water management and this memo section discusses both storm water management and grading and sediment erosion control plans). |
Catoctin Power shall prepare and implement stormwater management plans (including grading, sediment and erosion control plans) in accordance with applicable federal, state and local laws. Catoctin Power shall submit the stormwater management plan to DPDR prior to the start of rough grading.
|
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-13 |
Require that NOx and VOC offsets be purchased from Frederick County sources, if available; if not available from Frederick County sources, then these offsets must be purchased from the geographically closest available source(s). |
Catoctin Power shall endeavor to obtain all required NOx and/or VOC offsets from sources in or near Frederick County, if reasonably commercially available. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
FC-14 |
Require that the project must comply with all PM2.5 ambient air quality standards in effect today and which might be required in the future if Frederick County is designated as a non-attainment area for PM2.5. |
Catoctin Power shall comply with any future Maryland Department of the Environment regulations that are related to emission of PM 2.5 (i.e., fine particulate matter with a diameter smaller than 2-1/2 microns) and that are applicable to the Project. |
Frederick County did not provide specific language for the Draft Condition Currently In The Record. Catoctin Power supports inclusion of this condition in the CPCN provided that the condition is written as set forth in the Proposed Final Condition.
Catoctin Power fully supports the Proposed Final Condition, and respectfully requests that the PSC include the Proposed Final Condition in any CPCN. |
Pending |
|
Don James |
||||
|
James-1 |
If Catoctin Power approves the Catoctin facility for construction, Catoctin Power shall hire an independent third party consultant to conduct quarterly air testing at a minimum of 3 locations surrounding the plant (one of which must be Carroll | |||